Update on Gipsy Patch Lane Underbridge Replacement

Griffiths - 16th October 2020

The following presentation describes the outline site works programme from October to December.

Download the PowerPoint presentation to view aerial progress photos from the end of August.

Outline Site Works Programme Oct 20 > Dec 20

Recent progress

  • Complete SPMT Roadway construction
  • Commence Wessex Water Foul Water Sewer Access Chambers 21st
  • Sat Night 19/20 - Install Temporary Catenary Wire Bridge
  • Sat Night 26/27 - Suspend Railway cables from Temp Bridge & Moving rails & other minor works

Oct 2020

  • Sat Night 3/4 Pre blockade surveys
  • Sat Night 10/11 Complete Track Access Ramp
  • Anti Graffiti coating to new bridge
  • Complete Wessex Water FWS Access Chambers
  • Blockade Preparations/Deliveries
  • 24th Commence Core Blockade Works

Nov 2020

  • 7th Complete Core Blockade Works
  • Excavate new Highway Alignment
  • Commence new highway drainage attenuation pipes

Dec 2020

  • Complete Drainage attenuation pipes
  • Install Highway Drainage & Manholes
  • Excavate new bridge wingwalls